Pemasangan 295 SBG Simpang Susun Semanggi Rampung

Semanggi Intersection Construction Reaches 75 Percent

As many as 295 units of segmental box girder (SBG) in two ramps of Semanggi intersection have been installed. Currently, construction progress reaches 75 percent.

We will also restore the condition of parks and roads which affected by the construction

Jakarta Bina Marga Dept. Head, Yusmada Faizal said, after SBG installation, his side will complete the other parts such as on off ramp, parapet (barrier), hot mix coating, traffic sign, and lighting for bridge.

"We will also restore the condition of parks and roads affected by the construction," he said, Wednesday (4/26).

July, Open Traffic at Semanggi Interchange Trialled

Related to bridge's lighting, he explained that its operation will be integrated with smart city system. Thus colors and patterns setting can be controlled depends on the theme through smart city system.

"We have two months to work it. According to plan, we will open traffic trial in July," he closed.

Linked News
Popular News indeks
  1. Jakarta Removes Gibran’s Portraits Across All Government Offices

    access_time16-11-2026 remove_red_eye1131 personFakhrizal Fakhri
  2. Transjakarta Offers Free Rides for Jakarta Vertical Run 2026 Participants

    access_time14-11-2026 remove_red_eye711 personAldi Geri Lumban Tobing
  3. Governor Approves Removal of Seven Unauthorized Houses on Dispora Land

    access_time13-11-2026 remove_red_eye683 personFakhrizal Fakhri
  4. Pramono Outlines Measures to Address Five Issues in Kramat Jati

    access_time13-11-2026 remove_red_eye656 personFakhrizal Fakhri
  5. Jakarta Esports 2026 Draws Enthusiastic Crowds at M Bloc Space

    access_time13-11-2026 remove_red_eye643 personTiyo Surya Sakti